Chart
Dead load D = 120 kip
Live load L = 80 kip
Factored load Pᵤ = 272 kip
This is an example. Type your own values to start a new problem.
U₁ (kip)
=
1.4
×
D (kip)
U₂ (kip)
=
1.2
×
D (kip)
+
1.6
×
L (kip)
Pᵤ (kip)
=
max(
U₁ (kip)
,
U₂ (kip)
)
P
Service load
calculated · kip
Formulas
P
=
D
+
L
200 = 120 + 80
U₁
=
1.4
×
D
168 = 1.4 × 120
U₂
=
1.2
×
D
+
1.6
×
L
272 = 1.2 × 120 + 1.6 × 80
Pᵤ
=
max(
U₁
,
U₂
)
272 = max(168, 272)
Assumptions
•
ACI 318-19 strength combinations (from ASCE 7) with dead and live load only: 1.4D and 1.2D + 1.6L.
•
D and L are service (unfactored) loads; their sum P sizes the footing on the allowable soil pressure.
•
The larger combination is Pᵤ; 1.4D governs only when L is less than D ÷ 8.
Step-by-step
WE KNOW
D = 120 kip, L = 80 kip
FIND
service load (P), combination 1 (1.4D) (U₁), combination 2 (1.2D + 1.6L) (U₂), factored load (Pᵤ)
Step 1 · Find service load (P)
Use P = D + L
The load the soil carries day to day: dead and live, unfactored.
P
=
120
+
80
P
=
200
kip
Step 2 · Find combination 1 (1.4D): U₁
Use U₁ = 1.4 × D
Dead load alone, raised by 1.4: it governs when there is little live load.
U₁
=
1.4
×
120
U₁
=
168
kip
Step 3 · Find combination 2 (1.2D + 1.6L): U₂
Use U₂ = 1.2 × D + 1.6 × L
Live load varies more than dead load, so it takes the larger factor, 1.6.
U₂
=
1.2
×
120
+
1.6
×
80
U₂
=
144
+
128
U₂
=
272
kip
Step 4 · Find factored load (Pᵤ)
Use Pᵤ = max(U₁, U₂)
The footing must carry the worse of the two, so the larger combination is Pᵤ.
Pᵤ = max(168, 272)
Pᵤ = 272 kip
Check
Put the numbers back in. Both sides should match.
200 = 120 + 80 ✓
168 = 1.4 × 120 ✓
272 = 1.2 × 120 + 1.6 × 80 ✓
272 = max(168, 272) ✓